Link Copied!

6,000億ドルの賭け:2026年がAIの「死の谷」である理由

2026年第1四半期の収益は、恐ろしい乖離を明らかにしました。ハイパースケーラーはAIインフラストラクチャに6,000億ドルを費やしていますが、グリッド変圧器のリードタイムが143週間であるということは、この資本が何年も座礁することを意味します。

🌐
言語に関する注記

この記事は英語で書かれています。タイトルと説明は便宜上自動翻訳されています。

夕暮れの砂漠にある未完成のデータセンター建設、座礁した資本を表現

BREAKING (Jan 29, 2026): Microsoft shares plunged 10% in a single session—erasing nearly $300 billion in market value—after reporting a massive surge in AI capital expenditures without a corresponding acceleration in cloud revenue.


The math finally broke.

For two years, the market accepted a simple equation: Money In ($) \rightarrow GPU Out (Compute) \rightarrow Profit ($). As long as Nvidia was shipping chips, the valuations held.

But on January 28, 2026, Microsoft reported earnings that revealed a terrifying new variable in that equation. They are spending money faster than they can physically deploy it.

The headline number, a projected $627 billion in aggregate Hyperscaler capex for 2026, is staggering. But the scariest number isn’t the dollars. It’s the 143 weeks.

That is the current lead time for a Generator Step-Up (GSU) transformer. Even if Microsoft writes the check in January 2026, the grid hardware necessary to turn those H100s on won’t arrive until late 2028.

Welcome to the “Valley of Death” for AI capital: a two-year window where $600 billion in investment sits as stranded, non-performing assets because physical reality has finally caught up to digital exuberance.

The Capex-Revenue Disconnect

To understand why the market panicked on January 29, analysts must look at the rate of change.

In 2025, Hyperscaler capex grew by 73%. In 2026, it is projected to grow another 36% to over $600 billion. The expectation was that revenue would accelerate in lockstep.

It hasn’t.

Microsoft’s Azure growth, while healthy at 38%, actually slowed relative to the capital intensity required to maintain it. The efficiency ratio is collapsing.

Capex Intensity=Capital ExpendituresTotal Revenue\text{Capex Intensity} = \frac{\text{Capital Expenditures}}{\text{Total Revenue}}

For a mature software company, this ratio should be 10-15%. For Microsoft and Meta in Q1 2026, it is approaching 45-50%. They are spending half of every dollar they make on infrastructure that, increasingly, cannot be turned on largely due to power constraints. This level of intensity has not been seen since the peak of the Telecom Bubble, when carriers like WorldCom pushed their ratios above 40% just before the collapse.

Investors realized that this isn’t just “investing for growth.” This is capital destruction. When capital is deployed but cannot generate revenue for multiple years, the Internal Rate of Return (IRR) plummets to negative territory.

The Depreciation Clock

The hidden killer in this equation is depreciation. Unlike fiber optic cables or railway tracks, which have useful lives of 20-30 years, AI hardware is a melting ice cube.

A state-of-the-art GPU cluster has an economic life of about 4 years. Accounting standards typically depreciate this hardware at 25-30% per year.

Consider the “Stranded Asset” scenario:

  1. Microsoft spends $10 billion on a cluster of next-gen GPUs in Q1 2026.
  2. The chips arrive, but the GSU transformer needed to connect the facility to the high-voltage grid is delayed until Q3 2028 (the 143-week lag).
  3. The GPU cluster sits idle in a climate-controlled (but unpowered) warehouse for 2.5 years.

By the time the power turns on in 2028, the hardware has depreciated by nearly 65% on the books. Microsoft has lost $6.5 billion in value before a single token is generated. Furthermore, the chips are now two generations behind the cutting edge, meaning they cannot command the premium pricing originally modeled. This “Depreciation Clock” turns aggressive investment into a financial black hole.

The Anatomy of a 143-Week Delay

Here is the current reality of the supply chain entering 2026:

Equipment TypeTypical Lead Time (2023)Current Lead Time (2026)
Dry Type Transformers12-16 Weeks50+ Weeks
Large Power Transformers40-50 Weeks128 Weeks
GSU Transformers60 Weeks144 Weeks

Source: PowerMag Q2 2025 Survey, NPC Electric

This means a customized data center approved in Q1 2026 cannot be fully energized until late 2028.

The “Too Little, Too Late” Expansion

To be fair, the industry is responding. On January 13, 2026, CES Transformers announced a massive $100 million expansion of their Markham, Ontario facility to triple production capacity. This is a primary outcome of market signals working.

But here is the catch: building a factory to build transformers also takes time. The new CES capacity won’t fully hit the market until 2027-2028. For the Hyperscaler attempting to deploy $150 billion in 2026, this relief arrives exactly two years too late. They are trapped in the gap between capital deployment and supply chain catch-up.

Why can’t the industry just “build faster”? The answer lies in the physics of the grid and the complexity of the supply chain.

A Generator Step-Up (GSU) transformer is not an off-the-shelf component. It is a massive, custom-engineered machine often weighing 200 tons. It requires two critical inputs that are in global shortage:

  1. Grain-Oriented Electrical Steel (GOES): The core of a transformer requires high-permeability steel to conduct magnetic flux efficiently. There are only a handful of steel mills in the world capable of producing GOES at the required purity. Ramping up a new GOES mill takes 3-4 years and billions in capex.
  2. Copper Winding Skill: Winding the coils for a high-voltage transformer is a manual, artisanal process. It cannot be easily automated. The labor force with the specialized skills to wind these massive coils is aging, and training new technicians takes years.

There is no “Moore’s Law” for heavy electrical equipment. You cannot software-optimize a 200-ton copper coil. The physical constraints are absolute.

The “Telecom Bubble” Parallel

History doesn’t repeat, but it rhymes. And this rhyme screams “2001.”

During the Telecom Bubble (1996-2000), carriers like Global Crossing and WorldCom spent nearly $1 trillion laying fiber optic cables across the oceans and continents. They were right about the future, as the world eventually needed all that bandwidth.

But they were wrong about the timing. They built 20 years of capacity in 4 years. The capital was spent, the debt was issued, but the revenue to service it didn’t materialize fast enough. The result was a wave of bankruptcies that wiped out trillions in shareholder value.

The industry is witnessing the exact same pattern with “Dark Silicon.”

The fiber remained dark because there wasn’t enough internet traffic yet. The silicon remains dark because there isn’t enough electricity.

The difference? Fiber in the ground does not rot. A GPU in a box does. The obsolescence risk makes the AI bubble potentially more destructive to balance sheets than the fiber bubble ever was.

Second-Order Effects: The Industrial Squeeze

This capital trap doesn’t just hurt tech shareholders. It is about to hurt everyone who buys electricity.

To bypass the grid queue, Hyperscalers are now buying “behind-the-meter” power generation. They are signing deals with nuclear plants (like Constellation Energy) and gas plants to take their output directly, removing that supply from the public grid.

This creates a bidding war for electrons that the broader economy cannot win.

  • Tech Giants: Can pay $0.15-$0.20 per kWh because their margins are high and AI inference is high-value.
  • Aluminum Smelters: Can only pay $0.04 per kWh before their business model breaks.
  • Manufacturing: Can only pay $0.07 per kWh.

As AI sucks up the baseload power capacity, industrial users are being priced out. Analysts forecast a wave of factory closures in 2026-2027, not because of labor costs, but because Amazon and Microsoft bought all the reliable electricity. The attempt by Amazon to buy the Talen Energy nuclear output in Pennsylvania was just the first shot in this war. Regulators pushed back, but the cash will eventually find a way to secure the power, likely by building dedicated, off-grid gas turbines that bypass utility regulations entirely.

The Investor Playbook

So, is the AI trade over? No. But the “easy money” phase of simply buying NVDA and MSFT is dead. The trade has shifted from the buyers of chips to the enablers of power.

  1. Short the Capex Spenders: Companies like Meta and Microsoft are entering a period of margin compression. Their depreciation costs are exploding while their revenue is capped by physical deployment limits.
  2. Long the Grid Bottlenecks: The companies that make transformers, switchgear, and copper wire have 3-year backlogs and infinite pricing power.
  3. Long Independent Power: Regulated utilities are slow, but Independent Power Producers (IPPs) like Vistra (VST) and Constellation (CEG) own the most valuable asset in the world right now: gigawatts of power that are already connected.

The “Valley of Death” will eventually be crossed. The transformers will be built, the power plants will come online, and the AI revolution will continue. But the bridge to get there is made of dead capital, and the toll is going to be higher than anyone expected.

Sources

🦋 Discussion on Bluesky

Discuss on Bluesky

Searching for posts...